Alias
Bar / Restaurant

Address: 79 Clinton St.
Ground Floor / Cellar Total sq. ft.: 1,500 sq. ft.

Design period: 1-1/2 month (2001 September – October)
Construction period: 3 month (2001 November – January)

New Construction:

 Design / Construction Management
 Coordination with all contractors / Shop drawings
 Material coordination
 Schedule control
 New Sub-floor and White maple & Walnut flooring
 Fire-rated walls and ceiling
 New H.V.A.C. system and Duct work
 Sprinkler work
 New Plumbing on ground floor / cellar
 Storefront / Glass work
 Upgrade AMP. / Lighting system
 All custom made Millwork / wood paneling
 Custom made steel work


 
   

 
 
  Copyright © T Murao design,inc all rights reserved