Construction period: 6 Month ( 2003 August – February )
Scope of work: Demolish all existing includes:
Storefront
Skylight
Flooring up to wood joist & level
Walls
Sprinkler system to accommodate new design
New Construction:
Design / Filling / Landmark approval
Material coordination
Theatrical Sound / Visual system
All custom made Millwork
Custom made steel work
Theatrical lighting system
New Terrazzo Floor with brass bar
New Glazing / Skylight
Ceramic tiles / Marble / Carpeting
New Duct / exhaust work
New plumbing
All new power system
IT system
Custom Glass partitions / Mirrors